October 17, 2024
October 17, 2024 – Paving Cross Trenches
October 18, 2024 – October 28, 2024 NO WORK PLANNED
October 29, 2024 - October 31, 2024 – Paving Main Line and Cross Trenches remaining phases
November 1, 2024 – final clean up, restoration and pavement markings
October 03, 2024
October 7 – October 11
Pave any remaining cross trenches binder flush in Phase 2 (Pleasant Street to Parkside Road)
Finish any remaining clean up in all three Phases
Pavers on site October 17 to mill and top cross trenches
Anything after October 11 will be final paving and clean up related. The crew might leave the site for a week or so while waiting for the pavers
(Main line in Phase 1 (Newport Intersection to Parkside Road) and Phase 2 ready October 30)
June 25, 2024
During a scheduled water shut off this morning the crew ran into unforeseen issues. In order to complete the intended work today part of Everett Park (up to Williams Street) will need to be shut down until noon. The crews are doing everything they can to have the water turned back on with little inconvenience. Thank you for your patience.