Two week outlook on the Main Street Project
August 31, 2024
Two week outlook for the Main Street Project
August 23, 2024
Recent News
- Commissioners Monthly Meeting update
- Commissioner' Meeting
- Results of March 19, 2024 Election/Annual Meeting
- 2024 Annual Meeting
- Annual Report
Related Links
Alert
Two week outlook on the Main Street Project
August 31, 2024
No work on Monday 9/2
9/3 to 9/6
Night work to install 12” water main in Phase 2 (Parkside Road to Pleasant Street).
Temporary pave trench Friday morning. Done paving around 12PM.
9/9 to 9/13 (return to day work)
Install fire hydrants in Phase 2 (Parkside Road to Pleasant Street).
Fill, flush, pressure test and chlorinate the newly installed 12” water main in Phase 2 (Parkside Road to Pleasant Street).
Pave in Phase 1 (Newport Road to Parkside Road) while waiting for Phase 2 (Parkside Road to Pleasant Street) water main sample results.
Start house services in Phase 2 (Parkside Road to Pleasant Street).
Pave all trenches by Friday.
Alerts
Two week outlook on the Main Street Project
August 31, 2024
No work on Monday 9/2
9/3 to 9/6
Night work to install 12” water main in Phase 2 (Parkside Road to Pleasant Street).
Temporary pave trench Friday morning. Done paving around 12PM.
9/9 to 9/13 (return to day work)
Install fire hydrants in Phase 2 (Parkside Road to Pleasant Street).
Fill, flush, pressure test and chlorinate the newly installed 12” water main in Phase 2 (Parkside Road to Pleasant Street).
Pave in Phase 1 (Newport Road to Parkside Road) while waiting for Phase 2 (Parkside Road to Pleasant Street) water main sample results.
Start house services in Phase 2 (Parkside Road to Pleasant Street).
Pave all trenches by Friday.
Two week outlook for the Main Street Project
August 23, 2024
8/26-8/30/24
Continue on Phase 2 (Pleasant Street to Parkside Road) mainline install
Set back to prep and permanently pave the Phase 1 (Newport Intersection to Parkside Road) trenches
Clean up road edge after pave
9/2-9/6/24
NO WORK Monday 9/2/2024 – Labor Day
Finish mainline install in Phase 2
Temp pave on Friday
Everett Park water
June 25, 2024
During a scheduled water shut off this morning the crew ran into unforeseen issues. In order to complete the intended work today part of Everett Park (up to Williams Street) will need to be shut down until noon. The crews are doing everything they can to have the water turned back on with little inconvenience. Thank you for your patience.